Development Management
Civic Offices, 2 Watling Street,
Bexleyheath, Kent, DA6 7AT
Tel: 020 8303 7777
www.bexley.gov.uk
m/r 25/00833/FULM Tel 020 8303 7777
y/r date 29th April 2025
The person dealing with this matter is James Hughes (e-mail: )
The Owner/Occupier
[Address redacted]
Dear Sir(s)/Madam
Manor Farm North Cray Road Sidcup
Construction and operation of a 200MW Battery Energy Storage System (BESS) for a temporary period of 40 years, including energy storage containers, transformers, inverters, switchgear, control building, internal access tracks, site access, earthworks, landscaping, and an underground cable connection route (approximately 1.45km in length) to Hurst Grid Substation, and associated infrastructure.
Please consider whether this application affects your property
You can view the application, and submit any observations on the proposal, using the Planning Application Information Online system on the Council’s website using the following link:- https://www.bexley.gov.uk/services/planning-and-building-control/planning/view-and-comment-planning-applications. If you do not own the property that you occupy, please notify the owner, as both of your comments are welcome.
Any observations you make should be submitted by 21st May 2025. Comments sent after this date will be taken into account provided they are received before the application is decided. All observations will be considered before the Council reaches a decision on the application. If you do write, your letter will be acknowledged; you will be notified if the application is referred to the Planning Committee when your comments may be quoted in the Committee report, and you will be notified of the Council’s decision in due course. Legislation requires the Council to make any representations received available for public inspection.
Yours faithfully,
[Signature]
Head of Development Management